DPWH schedules road repairs from Nov 28 up to Dec 1, 2014

DPWH schedules road repairs from Nov 28 up to Dec 1, 2014 image

Text: Marcus De Guzman / Photos: | posted November 27, 2014 13:27

Road repairs will start at 10:00PM and end at 5:00AM

The Department of Public Works and Highway recently announced that they will conduct a series of road repairs and reblockings that will affect some major roads during the weekend.

Scheduled to commence from November 28 – December 1, 2014, 10:00PM – 5:00AM, the following roads that will repaired by the DPWH will be the following:


1.)Along Fairview Ave. from Carino Street to Marlboro Street (3rd lane)

2.)Along Mindanao Ave. from Road 8 to North Avenue (1st lane)

3.)Along Araneta Ave. from Calamba Street to Quezon Ave. (1st lane)


1.)Along C.P. Garcia Ave. from D. Castaneda to Velasquez Street (3rd lane)

2.)Along Quirino Highway from Camachille Street to Teacher's Bliss (2nd lane)


1.)Along Batasan Road from Civil Service Commission to DSWD (2nd lane)

2.)Along Congressional Ave. (2nd lane)


1.)Along Congressional Ave. Extension from Luzon Ave. to Miranila Subd. (3rd lane)

2.)Along Aurora Blvd. from G. Baldovino to C-3 / Gregorio Araneta Ave.